Process step re-order issue with upgraded projects

Hi guys,

I’m running into a bit of a problem while attempting to change the order of steps within the Process tab.

For example, if I have 5 steps in my process and I attempt to move step 4 to position 2, the step that was previously in position 2 drops to position 5 (i.e. rather than steps 2 & 3 moving to position 3 & 4).

It seems to happen on any project that existed prior to the upgrade to Octopus 2.0; projects created since then don’t seem to be affected.

My client is currently on version 2.3.6. Let me know if I can provide any additional detail.

Thanks,
Dan

Added work-around
Edit the deploymentprocess-projects-[number] ravendb document manually to move the step items around.