Hi! I have three steps. 1 and 2 run in parallel. I am not sure when step 3 will start. Will it start immediately after the end of step 2? Or after the end of both steps 1 and 2?
Hi Alew,
Thanks for getting in touch,
If the third step you have has a Run Condition
of Success: only run when previous step succeed
then this step will only action when both Steps one & two are successful, though to answer your question more directly, Step three will start when Step two is complete.
I hope this helps!
If you require any further assistance or clarification, please let me know
Kind Regards,
Reece